Written by Pete Braun | Nov 23, 2026, 3:00:02 PM

Short answer: It depends on the floor plate, the number of stories, crew size, weather, and how finished the drawings are when framing starts. Be careful with anyone who quotes a number without seeing the plans. The biggest factor is where the work gets done. Stick framing builds every wall on the deck, one floor at a time. Panelized cold-formed steel (CFS) builds the walls in a shop while site work is still happening, so the field crew just sets them. That's why we can promise to enclose in half the time, guaranteed.

You save even more time when the panels show up with more of the wall already done. That means the air/vapor barrier (A/VB) applied in the factory, window openings wrapped and blocked, and structural steel built in. Compared with a concrete frame, load-bearing CFS lets more of the structure, exterior wall, and envelope work overlap. And if you prefer a concrete frame, prefab CFS infill walls between post-tensioned (PT) concrete floors can still speed up enclosure.

This is how we explain the timeline to teams planning a 4–12 story apartment building or hotel.

What does "framing a mid-rise" actually include?

First, get clear on scope. People use "framing" to mean different things. For a load-bearing mid-rise, framing usually covers:

  • Load-bearing walls on every floor
  • Exterior walls on every floor
  • Floor systems between levels
  • Roof trusses and roof framing
  • Openings, headers, hold-downs, and lateral bracing or shear walls
  • Sheathing to get the building ready for the envelope

Then there's the work that usually follows framing on site: the air/vapor barrier, window prep, and steel pieces like brick relief angles. With panelizing, much of that can move into the shop too.

When we say panelized, our scope includes all the exterior walls: load-bearing, non-load-bearing, infill, and bypass. Some panel suppliers only provide the load-bearing exterior walls. That leaves the rest of the exterior to be stick-framed in the field, so the building doesn't get enclosed any faster, and their price looks cheaper only because the scope is incomplete. When you compare bids, compare the scope line by line.

"Enclosed" is the milestone that matters most. It means the structure is up, the roof is on, and the building is closed in enough for interior trades to start working without worrying about weather. Everything after that (MEP rough-in, drywall, finishes) waits on it.

How long does stick-built framing take?

With stick framing, crews bring loose studs and track (or lumber) to each floor. Then they lay out, cut, assemble, stand, plumb, and brace every wall by hand. The next floor can't start until the one below is framed and decked. So the schedule is basically:

(time per floor) × (number of floors) + roof

Time per floor depends on how productive the crew is that day. It moves with weather, manpower, how fast field questions get answered, and how much rework comes up. On a 6-, 8-, or 10-story building, small slips on each floor stack up into weeks.

And framing is only the first pass. After the walls are up, crews still have to come back for the air/vapor barrier, window prep, and steel. That's more trades on the outside of the building, often working from lifts.

There's a hidden cost too: the floor is the workshop. Material is stacked on the deck, cutting happens there, and other trades often can't get close until the framers move up.

How long does panelized framing take?

Panelized framing splits the work in two:

  1. In the shop: walls are built from the engineered shop drawings to tight tolerances, with openings, headers, and connections already in place. Roof trusses get built the same way.
  2. In the field: a local framing crew sets panels with a crane, connects them, and moves to the next floor.

The key is that shop fabrication runs in parallel with site work. While the foundation, podium, or first-floor slab is going in, panels for the upper floors are already being built. When the deck is ready, the walls are on site, labeled and sequenced in the order they'll be set.

So on a panelized job, each floor mostly comes down to setting the panels, connecting them, and moving up. The wall building already happened in the shop.

That per-floor set time is much shorter and more predictable than stick-framing the same floor, because the measuring, cutting, and assembling is already done. On Metreau, with seven stories of load-bearing CFS over a precast concrete podium, another level was completed every 2 weeks, walls and floors included.

How much more time do you save when panels include the A/VB and structural steel?

Quite a bit. Every scope you move into the shop is one less pass on site. The work happens in parallel, before the panel ever ships.

Our panels can arrive with more than framing and sheathing. Depending on the project, that can include:

  • Air/vapor barrier applied in the factory
  • Wood window blocking, with openings wrapped and ready for windows
  • Exterior continuous insulation (ci), installed in the shop together with the A/VB, plus brick ties
  • Structural steel, such as HSS members
  • Steel brick relief angles
  • Temporary window enclosures, when windows won't be ready right away

A few projects show what that adds up to:

  • Milwaukee Ballet: Fast panel setting alone gave a 3-week gain on the schedule. Combining other components (wood window blocking and temporary enclosures) brought the total to 6 weeks saved. A 40-day enclosure schedule was finished in just 7 days.

  • Lincoln Academy School (112,000 sf): The panels included wood window blocking, A/VB, structural steel HSS, and steel brick relief angles. We used CFS prefab as much as possible on the exterior framing. Interior trades started 7 weeks early, cutting the schedule time in half.

  • Wilderness Fly Theater (5 stories, 24,000 sf): Panels included A/VB, structural steel HSS, and temporary window enclosures. At 54 feet tall, they're our largest panels to date. Last-minute design changes were handled with on-site field modifications. As Frank Gauger, Project Manager at Holtz Construction, put it: "During the Wall-tech design process, there were many changes to the building coming to us from the A/E. However, that did not slow the project down. Panels arrived at the site, panels were installed, and we were getting enclosed allowing other trades to start their work."

Neither of the first two is a multifamily building. The idea carries over, though: the more scopes you combine, the more time you take off site. Multifamily and hotels repeat the same wall types floor after floor, which suits this kind of shop work well.

There's no exact figure for how much time factory A/VB saves on its own. On a large project we recently completed, it was estimated that factory A/VB and enclosure sequencing saved about 4 to 6 months, because interior trades could start much earlier.

Why apply the air/vapor barrier in the factory?

The A/VB is what makes a building weather-tight. On a typical job, crews apply it after framing, from lifts or scaffolding, floor by floor, in whatever weather shows up. Doing it in the factory changes that.

Every window opening comes wrapped and ready. We add the A/VB and window blocking in the shop. Each opening arrives wrapped and ready for the window. So window crews can start right after the walls are set, without waiting on a separate wrap-and-prep pass.

Better quality control. Panels are built off-site in a controlled environment. The A/VB goes on a flat panel at a workstation, not on a vertical wall from a lift. Laps, seams, and opening wraps are easier to see and fix before anything ships. Steel framing also won't warp, split, or crack when exposed to the elements, so the surface behind the membrane stays true.

Weather matters less. Rain, wind, and cold can stall field-applied barriers. In the shop, the work keeps going. On Metreau, the building dried in within 20 weeks, even with 2 blizzards.

Cleaner sequencing. Without a separate A/VB phase after framing, the path to enclosure is shorter. The next trades can line up behind the panels instead of behind a barrier crew. That's the point of our last step to prefab success: be ready with all trades to take advantage of the faster enclosure, and update the schedule to match.

Fewer trades and lifts on site. When framing, A/VB, window blocking, and steel come in one panel, fewer separate crews need to work the exterior. That means less congestion, less noise for the neighbors, and fewer people to coordinate around the crane. It also helps with the skilled labor shortage and makes on-site work more productive.

Simpler inspections. A/VB work done in the shop can be checked panel by panel, at ground level, before it's installed.

Earlier dry-in. Panels with A/VB and wrapped openings close the building in sooner. Interior trades start sooner. On Lincoln Academy, that meant starting interior work 7 weeks early. When windows aren't ready yet, panels can come with temporary window enclosures, so the building still closes in on time.

Safety. Less exterior work at height means less time on lifts and scaffolding. Improved safety performance is one of the main benefits of prefabrication over stick framing.

Wall-tech installs several different types of A/VB in the shop. The right one depends on the wall design and cladding.

Insulation can go on in the shop too. Wall-tech can install an exterior continuous insulation (ci) system together with the A/VB in the shop. That takes another exterior pass off the site. On an upcoming large project, the customer estimates about $1 million in savings from using Wall-tech's factory insulation and A/VB system instead of a traditional field-installed A/VB and insulation.

How does panelized CFS compare with a concrete structure?

Concrete is a common choice for mid-rise buildings, and some developers really like it. We work both ways. We can build the structure itself in load-bearing CFS, or we can build prefab CFS infill walls for a concrete frame.

Load-bearing CFS: the phases overlap. With a cast-in-place, post-tensioned concrete frame, the work usually runs in order: engineering and foundations, the superstructure, the exterior walls, the A/VB and roofing, then enclosure. With load-bearing CFS, the panels are the structure. They're also the exterior wall. They're built in the shop while foundations go in, and they can arrive with the A/VB already on. Because the structure and exterior wall arrive as one piece, and much of the envelope work is done before the panels ship, more of those phases overlap. The more they overlap, the shorter the path to enclosure.

Prefer a concrete frame? Panelized infill still speeds up enclosure. Wall-tech also does infill framing: prefab CFS exterior wall panels set between post-tensioned (PT) concrete floor systems. The walls are built in the shop while the concrete frame goes up, so the field crew sets them instead of building them on each floor. That can also save significant time on the way to enclosure.

When the budget is the problem, a CFS redesign can help. The Courtyard by Marriott in University Heights, IA is a 7-story, 115,000 sf hotel. As a precast concrete structure, it came in way over budget. Wall-tech provided engineer of record (EOR) services with a complete redesign in load-bearing CFS, with air/vapor barriers, prefabricated C-joist CFS floor cassettes with structural floor sheathing, and integrated structural steel. We also prefabricated and installed the systems. The redesign saved about $10 per square foot, roughly $1.15 million (approximate) on the 115,000 sf building, and brought the project back in budget. Without it, the developer couldn't have made the pro forma work, and the project would have been canceled. The hotel is now complete.

Panelized vs. stick-built vs. concrete: side-by-side

Factor Stick-built (field-framed) Panelized CFS Post-tensioned concrete frame
Where the structure is built On the deck, floor by floor In the shop, before and during site work Formed and poured on site, floor by floor
When structural work can start After each deck is ready Fabrication starts while the foundation and podium are underway After foundations, one floor at a time
Exterior wall Framed in the field The load-bearing panels are the exterior wall Its own phase after the superstructure; can be prefab CFS infill panels
Air/vapor barrier Field-applied after framing Can be factory-applied, openings wrapped Usually its own phase, along with roofing
Exterior continuous insulation Field-installed after framing Can be shop-installed with the A/VB Field-installed after the exterior walls
What the field crew does Layout, cut, assemble, stand, plumb, brace Set, plumb, connect Form, reinforce, pour, then build or set the walls
Weather sensitivity High, since all assembly happens outside Lower, since assembly happens indoors Site-cast work is weather-dependent; infill panels are built indoors
Consistency floor to floor Depends on crew and conditions Panels built to the same engineered dimensions Depends on crew and conditions
Deck congestion Heavy (material and cutting on the floor) Lighter (panels arrive staged for install) Formwork and pours on each floor
Design timing Can be figured out in the field (often the problem) Needs decisions made earlier Structure designed up front; infill panel decisions made early
Path to enclosure Framing, then separate A/VB, insulation, and window prep passes Panels arrive with much of the envelope done, then set and enclose Superstructure, then exterior walls (or infill panels), then A/VB and roofing, then enclosure
Time to enclosure Baseline Wall-tech guarantees half the time of stick-built Phases mostly run in sequence; panelized infill helps speed up enclosure

Why is panelized framing faster?

Five reasons, roughly in order of how much they matter:

  1. Parallel work. The biggest gain. Wall building no longer waits for the deck.
  2. More scopes in one panel. A/VB, window blocking, insulation, and steel go on in the shop, not in extra passes on site.
  3. Fewer decisions in the field. Questions get answered in shop drawings, not on a ladder. Fewer RFIs mid-frame means fewer stalls.
  4. Weather stops mattering as much. A rainy week slows the crane, but it doesn't stop wall assembly.
  5. Repetition. Multifamily and hotels stack the same unit types floor after floor. Shop production is built for that.

What can and can't be panelized?

Not everything should be prefabricated. Part of our job is helping the team draw that line. Generally:

Good candidates for panelizing:

  • Repetitive load-bearing exterior, corridor, and demising walls
  • Bypass exterior walls
  • PT infill exterior walls (between post-tensioned concrete floors)
  • Floor and roof trusses
  • Standard window and door openings
  • A/VB, window blocking, continuous insulation, and steel on exterior panels

Often better built in the field:

  • One-off conditions, odd angles, and transitions
  • Areas where final dimensions depend on work by other trades
  • Small infill pieces where the crane time isn't worth it

The cleaner the stacking and the more repetition in the plan, the more you can move into the shop. Small layout changes early in design, like lining up bearing walls or standardizing openings, can open up a lot more prefab. That's part of the value engineering we do with design teams.

What slows panelized jobs down, and how do you avoid it?

Panelizing isn't magic. When jobs lose time, it's usually for the same few reasons:

  • Late design decisions. Panels get built from approved shop drawings. If openings or wall locations are still changing, fabrication waits. Lock the stacking walls and openings early.
  • Slow shop drawing approvals. Build the review time into the schedule and keep the turnaround tight.
  • No crane or laydown plan. Panels need a pick plan, a crane that can reach, and somewhere to stage deliveries. Sort out site logistics before the first truck shows up.
  • Delivery out of sequence. Panels should arrive in the order they'll be set. The first panel built or loaded isn't always the first panel set. That takes coordination between the shop, the GC, and the framing sub.
  • Bad slab or podium tolerances. Shop panels are accurate. If the surface they land on isn't, you'll spend time shimming and adjusting. Keep it flat, square, and plumb. Check anchor locations and elevations before setting starts.
  • Not enough work ready behind the panels. Prefab is fast-paced. If the next trades aren't ready, the time you gained sits idle.

This is why we put so much effort into the install gameplan: sequencing, delivery schedule, crane picks, connection details, and who does what between our team, the GC, and the local framing sub.

What does "Enclose in Half the Time. Guaranteed." mean?

It means we put a promise behind the schedule. The comparison is time to enclosure with our panelized CFS walls and trusses versus conventional stick-built framing for the same building. Industry groups like the Steel Framing Industry Association (SFIA) publish case studies on this kind of mid-rise CFS work.

We can stand behind it because of how we organize the work. We build walls while the site is being prepared. The field crew sets instead of builds. And the plan is worked out before anyone's on a ladder.

What does this look like on a real project?

Metreau Apartments in Green Bay, WI is a 107-unit luxury apartment project with Catalyst Construction as general contractor and Dermond Property Investments as developer. It's seven stories of load-bearing CFS over a precast concrete podium, and it opened in fall 2016.

  • 7 stories of load-bearing CFS walls and floors
  • 114,000 sf of CFS framing
  • 1,106 wall panels and 670 floor panels
  • Another level completed every 2 weeks
  • An eight-person crew erected the CFS walls and floor systems in 14 weeks
  • Building dried in within 20 weeks, even with 2 blizzards

By panelizing the entire job and delivering the building earlier, we estimate the developer saved about $250,000 in construction and carrying costs.

How should you plan a panelized framing schedule?

A practical sequence:

  1. Bring the panel partner in during early design. Decide what gets prefabricated and what doesn't while changes are still cheap.
  2. Lock stacking walls and openings. These drive the shop drawings.
  3. Decide which scopes go in the panels. A/VB, window blocking, continuous insulation, and structural steel each take work off the site.
  4. Schedule shop drawings and approvals so fabrication can start while foundations and the podium are going in.
  5. Build the install gameplan with the GC and framing sub: crane, laydown, delivery sequence, and connection details.
  6. Verify the deck before each floor is set.
  7. Set, connect, repeat, then trusses and enclosure.
  8. Have the next trades ready. Windows and interior crews should be scheduled to start as soon as the walls are set.

FAQ

How long does it take to frame a 6-story building?

It depends on the floor plate, crew, weather, and how complete the design is. Any honest answer starts with the drawings. What we can say: panelized framing takes the wall building off the critical path, and we guarantee enclosure in half the time compared to stick-built.

Is CFS framing faster than a concrete structure?

It can be. With a concrete frame, the structure, exterior walls, A/VB, roofing, and enclosure usually happen in sequence. With load-bearing CFS panels, the structure and exterior wall are one piece, built in the shop while foundations go in, so more of those phases overlap. How much faster depends on the building. And if you prefer concrete, panelized CFS infill walls can still speed up enclosure.

Can you panelize the infill walls between post-tensioned concrete slabs?

Yes. Wall-tech does infill framing with prefab CFS exterior wall panels set between post-tensioned (PT) concrete floor systems. You keep the concrete frame, and the exterior walls are built in the shop while the main structure goes up. That can also save significant time on the way to enclosure.

Can a building designed in concrete be redesigned in CFS?

Often, yes. The Courtyard by Marriott in University Heights, IA (7 stories, 115,000 sf) came in way over budget as a precast concrete structure. We provided EOR services with a complete redesign in load-bearing CFS, with A/VB, C-joist floor cassettes, and integrated structural steel. It saved about $10 per square foot, roughly $1.15 million (approximate), and kept the project from being canceled. Bring us in early so a redesign doesn't hold up the design schedule.

How much time does a factory-applied air/vapor barrier save?

It takes a whole field pass off the schedule, and that work happens in parallel in the shop. There's no exact figure, and the savings depend on the project. On a large project we recently completed, it was estimated that factory A/VB and enclosure sequencing saved about 4 to 6 months, because interior trades could start much earlier.

Can windows go in right after the walls are set?

Yes. The openings arrive wrapped with A/VB and blocked, ready for windows. If the windows aren't on site yet, panels can come with temporary window enclosures so the building still closes in.

Is a factory-applied A/VB better quality than a field-applied one?

It's built in a controlled environment, on a flat panel, out of the weather. That makes laps, seams, and opening wraps easier to get right and easier to check before the panel ships. Then, all that's left is to "stitch up" the seams on-site after installation.

Can continuous insulation be installed in the shop?

Yes. Wall-tech can install an exterior continuous insulation (ci) system together with the A/VB in the shop. On an upcoming large project, the customer estimates about $1 million in savings from using our factory insulation and A/VB system instead of a traditional field-installed A/VB and insulation.

Can structural steel be built into the panels?

Yes. We've built HSS steel and steel brick relief angles into panels, which takes more work off the site.

When do panels need to be ordered?

Early enough for shop drawings to be approved, MEP clash detection and coordination to be completed, and fabrication to run while the foundation and podium go up. Bring your panel partner in during design, not after the framing bid.

Who installs panelized walls?

Local framing subs, working with the GC. The panels arrive built, labeled, and sequenced, and the crew sets and connects them following the install plan.

Does weather affect panelized framing?

Less than stick framing. Wall assembly, the A/VB, and continuous insulation happen indoors, so weather mostly affects crane work and setting, not production.

Can floor and roof trusses be prefabricated too?

Yes. CFS floor and roof trusses are built in the shop along with the wall panels, which helps get the roof on and the building enclosed sooner.

Do I need to redesign my building to panelize it?

Usually not a full redesign. Small adjustments, like aligning stacking walls and standardizing openings, often enable more prefab and greater savings. That's the value engineering conversation to have early.