Across senior living, multifamily and hotel projects, Wall-tech has helped teams match the floor system to the building — span, fire rating, sound, schedule, budget and finishes — and prefabricates load-bearing cold-formed steel walls and floor cassettes so floors and walls can go up together. There is no single best floor. Wall-tech, in business since 1984, works with several systems so you can pick the one that fits, rather than force one approach onto every building.
The right floor is a project decision, not a catalog default. A short, repetitive hotel bay, a longer apartment span, a corridor that needs more room for mechanical, electrical and plumbing, or a building that wants a concrete floor feel will not all land on the same system. Wall-tech's prefabrication services cover the walls, the floor systems and the roof trusses, and we will help you weigh the options against the drawings you actually have.
Floor speed is not only about the floor
Floor speed matters beyond the floor itself. The faster a floor system goes in, the sooner the wall panels for the next level can be set. That is why Wall-tech builds prefab load-bearing cold-formed steel (CFS) wall panels and floor cassettes, and works with several floor systems, instead of pushing one system.
Wall-tech floor cassettes, which are prefabricated CFS floor panels, are built for fast crane pick-and-set cycles. The panels are built in the shop, then set on site by crane, so more of the floor work happens off the deck. That means less on-site labor for the floor framing, and less of that work sitting in the weather as stick-built joists. Once a level is set, the next prefabricated walls can go up, and interior trades can start sooner on the floors already in place. You can see the shop-to-site sequence on our process page.

A Wall-tech floor cassette, a prefabricated CFS floor panel, set by crane.
That cassette approach is a natural fit for the C-joist systems described below. The dry floor with C-joists (DF-J) builds easily into floor cassettes, and the gypsum-topped floor with C-joists (GT-J) prefabricates well as floor cassettes. The sections on those two systems lean into that speed. Other systems in this comparison have their own strengths — longer spans, open webs for MEP, or a high-mass concrete floor — and those matter just as much when the building calls for them.
Wood framing is a good solution for many building types, including many shorter multifamily buildings, but it has limits as buildings get taller or need a non-combustible construction type. For a broader look at how developers are weighing cold-formed steel against wood, and at what developers worry about with prefab CFS, we have separate posts. This one stays on the floor.
A note on UL designs listed on drawings
Floor-ceiling assemblies are often specified by a UL design number on the drawings. In most cases, that number is one way to meet the required fire-resistance rating. Other listed assemblies may meet the same rating. Most UL designs aren't tied to one supplier, so the GC has choices. If you'd like to compare options, ask the engineer of record and design team whether an alternate listed assembly is acceptable for your project. Wall-tech is happy to share the assemblies we work with to support that conversation.
The UL designs named in this post are a shortcut to common systems. They are common examples, not a complete list. Other UL-listed designs are available. We are not adding design numbers beyond the ones in the comparison. If your drawings show a different listed assembly, or you want to compare alternates, that is a conversation with your design team and with Wall-tech — not something to freeze from a blog post.
Ratings and minimums below are summarized from those example UL listings. Each listing has additional requirements and alternates. Always confirm against the current UL listing, your project drawings, and the authority having jurisdiction. Pros and cons are general and vary by project.
The systems at a glance
| System | Basic makeup (top to bottom) | UL designs (common examples, not a complete list) | Listed rating† | Typical sound (STC / IIC)‡ | Typical strengths | Typical trade-offs | Often a good fit for |
|---|---|---|---|---|---|---|---|
| DF-J Dry Floor, with C-joists | 3/4" non-combustible structural subfloor · Wall-tech CFS C-joists (24" o.c.) · 3-1/2" glass fiber batts · resilient channel · 5/8" gypsum board (1 or 2 layers) | UL H509, UL H505, UL H531* | H509: 1, 1-1/2 or 2 hr; H505: 1 or 2 hr; H531*: 2 hr; unrestrained | STC 54–61, IIC 27–72 (finish dependent) | Lightest option, no wet trades. Builds easily into floor cassettes. | Limited room for MEP. Joist depth may limit spans. | Low- to mid-rise where weight, simplicity and dry construction lead |
| DF-T Dry Floor, with trusses | 3/4" non-combustible structural subfloor · Wall-tech CFS trusses (min 12" deep, 24" o.c.) · 3-1/2" glass fiber batts · resilient channel · 5/8" gypsum board | UL H531, UL H505 | H531: 2 hr; H505: 1 or 2 hr; unrestrained | STC 54–61, IIC 27–72 (finish dependent) | Longer spans for the weight; open webs for MEP. No wet trades. | Deeper floor, taller floor-to-floor. | Most similar to traditional wood-framed multifamily construction |
| GT-J Gypsum-Topped Floor, with C-joists | Gypsum floor topping (1-1/8" min with 8" joists) · 9/16" corrugated steel deck · Wall-tech CFS C-joists (min 8", 24" o.c.) · 3-1/2" insulation · resilient channel · 5/8" gypsum board | UL G564 | 1 or 2 hr unrestrained | Similar assemblies: STC 59–62, IIC 41–76 (finish dependent) | Topping adds mass for sound control. Prefabricates well as floor cassettes. | Topping is a wet trade with pour and cure time. Heavier than a dry floor. Limited room for MEP. | Multifamily and hotels with moderate spans |
| GT-T Gypsum-Topped Floor, with trusses | Gypsum floor topping · 9/16" corrugated steel deck · Wall-tech CFS trusses (24" o.c.) · 3-1/2" insulation · resilient channel · 5/8" gypsum board | UL G564 | 1 or 2 hr unrestrained | STC 60–62, IIC 46–77 (finish dependent) | Topping adds mass for sound control. Longer truss spans and open webs for MEP. | Topping is a wet trade with pour and cure time. Deeper and heavier than a dry floor. | Longer-span units and corridors |
| CT-T Concrete-Topped Floor, with trusses | 2" to 3" concrete topping · welded wire fabric · corrugated steel deck · Wall-tech CFS trusses or CFS joists (to 48" o.c.) or steel joists (to 52" o.c.) · resilient or furring channel · 1 or 2 layers gypsum board | UL G542, UL G531, UL G555 | 1 or 2 hr (G531 also 1-1/2 hr); restrained and unrestrained | STC 50–56, IIC 25–68 (finish dependent) | Durable, high-mass concrete floor. Wide truss spacing. Open webs for MEP. Can be combined with clear-span decking in the corridor for more MEP room. | Heaviest option; adds load to walls and foundations. Concrete placement and cure time. | Projects wanting a concrete floor feel, durability or extra mass, and longer spans with lots of MEP |
| CT-CS Concrete-Topped Floor, clear span | Normal-weight concrete topping (3,000 psi) with welded wire fabric · structural metal decking (1-1/2", 2" or 3" deep, min 22 ga) · suspended grid ceiling · 5/8" gypsum board | UL D502** | 1-1/2 or 2 hr, restrained and unrestrained (1 hr with insulation) | Similar decks: STC 56–60, IIC 36–60 (finish dependent) | Simple deck-and-concrete floor. No joists to frame. Thinner overall floor system depth. Can be combined with clear-span decking in the corridor for more MEP room. | Spans limited by the deck. Concrete placement, cure time, and shoring. | Hotels with short, repetitive spans |
*EJ = engineering judgment. UL H531 is listed with CFS trusses; its use with C-joists (DF-J) is covered by engineering judgment.
**D502: listed with a suspended grid ceiling; a resilient channel ceiling requires EJ.
†Ratings and minimums are summarized from the example UL listings. Each listing has additional requirements and alternates. Always confirm against the current UL listing, your project drawings, and the authority having jurisdiction.
‡Typical sound ranges are from published tests on matching or similar assemblies and depend on the finish floor, sound mat and ceiling. See the sound ratings section below.

Cold-formed steel floor and wall framing in a mid-rise apartment building.
Sound ratings for each floor system
Two numbers show up on almost every multifamily floor conversation: STC and IIC. STC, or Sound Transmission Class, is the airborne rating (voices, television, music). IIC, or Impact Insulation Class, is the impact rating (footsteps, chairs sliding, dropped objects). A higher number is better, and a floor can do well on one and fall short on the other.
That split is why the finish floor matters so much. A hard surface can still have a solid STC, because mass and the ceiling help with voices and TV, but the same floor may have a low IIC until you add a sound mat or a softer finish such as carpet and pad.
For dwelling units and sleeping units, the International Building Code, Section 1206, sets a minimum of STC 50 and IIC 50 when the assembly is tested in the laboratory, or 45 when it is field-tested in the finished building. Those are code minimums, not comfort targets, and some projects aim higher. The figures below are typical tested-assembly examples from the Steel Framing Alliance's February 2017 fire and acoustic guide for cold-formed steel assemblies, plus other published tests on matching or closely matching assemblies. They are not guarantees for every building. Confirm the numbers against the current acoustical test reports, your design team and the authority having jurisdiction.
DF-J — Dry floor, with C-joists. Published manufacturer tests on H505-type floors (a 3/4" non-combustible structural cement panel on cold-formed steel joists, 3-1/2" fiberglass, resilient channel and 5/8" Type C gypsum) measured STC 54 and IIC 27 with a bare floor; about STC 56 to 61 and IIC 51 to 57 with a hard surface finish over a sound mat underlayment, with the upper end using two layers of gypsum board; and about STC 56 to 57 and IIC 65 to 72 with carpet and pad. A bare or hard floor needs a sound mat to reach the code minimum IIC 50, and results depend on the sound mat or underlayment and on one versus two layers of gypsum board.
DF-T — Dry floor, with trusses. The published manufacturer tests above are on the joist version of the H505 floor; the truss version is similar in makeup, so those ranges are a reasonable guide, but they are not a separate truss test. A bare or hard floor still needs a sound mat to reach the code minimum IIC 50.
GT-J — Gypsum-topped floor, with C-joists. The 2017 industry guide does not list STC or IIC values for the example UL design (G564). Published tests on similar gypsum-topped steel-joist floors are about STC 59 to 62 and IIC 41 to 76, depending on the topping, sound mat and finish floor; some of those tests used a thicker topping and deeper joists than the minimums in this comparison. Ask Wall-tech for project-specific values.
GT-T — Gypsum-topped floor, with trusses. Published tests on a G564 steel-truss assembly with a gypsum topping, a sound mat, resilient channel and 5/8" gypsum board measured about STC 60 to 62, and IIC 46 with the mat but no finish floor, IIC 51 to 57 with a hard finish, and IIC 77 with carpet and pad. A finish floor is what takes the impact rating over the code minimum IIC 50.
CT-T — Concrete-topped floor, with trusses. The 2017 industry guide does not list ratings for two of the example designs (G542 and G531); for UL G555 and closely related concrete-topped listings, it reports about STC 50 to 56 and IIC 25 to 68, with the low impact end typical of a bare topping and the high end depending on the finish floor and underlayment. Ask Wall-tech for project-specific values.
CT-CS — Concrete-topped floor, clear span. We did not find a complete laboratory STC and IIC pair for the example UL D502 assembly described in this post. Other published concrete-on-steel-deck floors with a gypsum ceiling in the 2017 industry guide are about STC 56 to 60 and IIC 36 to 60, or an estimated IIC 70 with carpet and pad, depending on the topping, ceiling, underlayment and finish floor. Ask Wall-tech for project-specific values.
If your drawings already have a sound target, or you want to compare assemblies, that is a conversation with your design team and with Wall-tech. We will help you match the floor, the ceiling and the finish to the rating the project actually needs.
DF-J — Dry Floor, with C-joists
The dry floor with C-joists is a light, dry assembly: a 3/4" non-combustible structural subfloor, Wall-tech cold-formed steel C-joists at 24" on center, 3-1/2" glass fiber batts, resilient channel, and 5/8" gypsum board in one or two layers. It is often a good fit for low- to mid-rise work where weight, simplicity and dry construction lead.
The benefits start with what you do not have to do on site. There are no wet trades in the floor itself, so you are not waiting on a topping pour or a cure window before the next step. It is the lightest option in this comparison, which can help where wall and foundation loads are a concern. And it builds easily into floor cassettes.
That last point is where the speed shows up. Wall-tech can prefabricate the DF-J floor as CFS floor panels, then set those cassettes by crane in fast pick-and-set cycles. Less floor framing is built in place, so there is less on-site labor and less of the floor sitting exposed in the weather. As soon as a level is set, the prefabricated walls for the next level can go up, and interior trades can start sooner on the floors already in place. Floors and walls move together, instead of the deck waiting on stick-built joists.
The honest trade-offs are the ones in the comparison. C-joists leave limited room for MEP compared with an open-web truss, and joist depth may limit spans. If the building needs longer spans or more space for ducts and piping in the floor, one of the truss systems below may be a better match. Common example UL designs for DF-J include UL H509, UL H505 and UL H531*; those are not a complete list, and other listed designs may be available.
DF-T — Dry Floor, with trusses
The dry floor with trusses keeps the same dry makeup — a 3/4" non-combustible structural subfloor, 3-1/2" glass fiber batts, resilient channel and 5/8" gypsum board — but it uses Wall-tech cold-formed steel trusses, minimum 12" deep, at 24" on center. It is often the system that feels most similar to traditional wood-framed multifamily construction, with steel trusses standing in for the wood floor framing many teams already know.
The benefits are span and access, without a wet trade. You get longer spans for the weight, and the open webs give MEP a path through the floor. There is still no topping to pour or cure, so the floor stays a dry operation. For apartment layouts that need to reach farther between supports, or corridors that have to carry more services, that combination is the point of this system.
The trade-off is depth. A deeper truss means a deeper floor and a taller floor-to-floor. That can be the right call when span and MEP win, and the wrong call when you are trying to keep the building shorter. Common example UL designs include UL H531, listed at 2 hours unrestrained, and UL H505, listed at 1 or 2 hours unrestrained. Those are examples, not a complete list.
GT-J — Gypsum-Topped Floor, with C-joists
The gypsum-topped floor with C-joists adds mass on top of a cassette-friendly C-joist frame: gypsum floor topping (1-1/8" minimum with 8" joists), 9/16" corrugated steel deck, Wall-tech cold-formed steel C-joists at an 8" minimum depth and 24" on center, 3-1/2" insulation, resilient channel and 5/8" gypsum board. It is often a good fit for multifamily buildings and hotels with moderate spans, when you want more sound control than a dry floor and you still want the floor to prefabricate well as cassettes.
The topping is the sound story. That extra mass is there for sound control, which matters in apartments where people live over and under each other. The framing side of the system still prefabricates well as floor cassettes, so you keep the same speed story as DF-J: shop-built CFS floor panels, fast crane pick-and-set, less on-site labor, less weather exposure for the framing, floors and walls going up together, and interior trades starting sooner on finished levels. The topping is a separate, later step, not a reason to stick-build the joists.
The trade-offs are real. The topping is a wet trade with pour and cure time, the floor is heavier than a dry floor, and C-joists still leave limited room for MEP. If you need the mass and you also need longer spans or more open webs, the gypsum-topped truss system is the next place to look. A common example UL design is UL G564, at 1 or 2 hours unrestrained. Other listed designs may be available.

Corrugated steel deck on prefabricated cold-formed steel walls, ready for a floor topping.
GT-T — Gypsum-Topped Floor, with trusses
The gypsum-topped floor with trusses uses gypsum floor topping, 9/16" corrugated steel deck, Wall-tech cold-formed steel trusses at 24" on center, 3-1/2" insulation, resilient channel and 5/8" gypsum board. It is often a good fit for longer-span units and corridors.
You keep the sound benefit of the topping — that added mass for sound control — and you add what the trusses are for: longer truss spans and open webs for MEP. That is the system to look at when the apartment or corridor spans past what a C-joist floor wants to do, but you still want a gypsum topping rather than a concrete floor.
The trade-offs follow the topping and the truss depth. The topping is a wet trade with pour and cure time, and the floor is deeper and heavier than a dry floor. A common example UL design is again UL G564, at 1 or 2 hours unrestrained, as an example rather than a complete list.
CT-T — Concrete-Topped Floor, with trusses
The concrete-topped floor with trusses is for projects that want a concrete floor feel, durability or extra mass, and longer spans with lots of MEP. The makeup is a 2" to 3" concrete topping, welded wire fabric, corrugated steel deck, Wall-tech cold-formed steel trusses or CFS joists (to 48" on center) or steel joists (to 52" on center), resilient or furring channel, and one or two layers of gypsum board.
This is a durable, high-mass concrete floor, and that mass is a feature, not a drawback, when the project wants it. Wide truss spacing and open webs give MEP room to run. This floor can also be combined with clear-span decking in the corridor, which creates more room for mechanical, electrical and plumbing. Used with Wall-tech prefabricated walls, it is one more way to complete the floor and keep the building moving; it is not a lesser stand-in for a full concrete structure, and it is not a reason to talk down concrete. Some buildings want this floor, and Wall-tech will help design to it.
The honest trade-offs are weight and the wet work. It is the heaviest option in this comparison, so it adds load to the walls and foundations. Concrete placement and cure time are part of the sequence. Common example UL designs include UL G542, UL G531 and UL G555, at 1 or 2 hours (G531 also 1-1/2 hours), restrained and unrestrained. Those are examples, not a complete list; other listed designs may be available.

Prefabricated walls and a finished floor level in a senior living corridor.
CT-CS — Concrete-Topped Floor, clear span
The clear-span concrete-topped floor is a simpler deck-and-concrete assembly: normal-weight concrete topping (3,000 psi) with welded wire fabric, structural metal decking (1-1/2", 2" or 3" deep, minimum 22 ga), a suspended grid ceiling and 5/8" gypsum board. It is often a good fit for hotels with short, repetitive spans.
The benefits are simplicity and depth. There are no joists to frame, and the overall floor system depth is thinner. For a building with short, repeating bays, that can be a clean way to get a concrete floor down and keep the floor-to-floor tight. It can also be combined with clear-span decking in the corridor, which creates more room for mechanical, electrical and plumbing.
The trade-offs are span and the wet work. Spans are limited by the deck, and you still have concrete placement, cure time and shoring. A common example UL design is UL D502**, at 1-1/2 or 2 hours, restrained and unrestrained (1 hour with insulation). D502 is listed with a suspended grid ceiling; a resilient channel ceiling requires engineering judgment. As with the other systems, that design is an example, not a complete list.
Send us the plans
Wall-tech will help you match the floor to the project, whether that is a dry C-joist cassette floor built for speed, a truss floor that reaches farther and leaves room for MEP, or a concrete-topped floor when you want the mass and the feel. You can see examples of the work on our Projects page, and we have written more about prefab CFS on mid-rise multifamily and about cold-formed steel and wood on mid-rise buildings if you want that context.
Tell us your span, fire rating, sound targets and schedule, and we will help you weigh the options. Send us your plans for a cost-efficient framing solution and a preliminary budget through our Contact Us page, or call 608-257-1595.
Let us know how we can help.
FAQ
Which floor system is best for my project?
There's no single best floor system. The right one depends on your span, fire rating, sound targets, schedule, budget, and how your building will be finished. Wall-tech works with several cold-formed steel floor systems, including dry, gypsum-topped and concrete-topped floors with C-joists or trusses, and floor cassettes where they fit. Send us your plans and we will help you weigh the options and offer a cost-efficient framing solution and a preliminary budget. Let us know how we can help.
What are Wall-tech floor cassettes?
Wall-tech floor cassettes are prefabricated CFS floor panels, built for fast crane pick-and-set cycles. They are built in the shop and set on site by crane, which means less on-site labor for the floor framing and less of that work sitting in the weather. The faster a floor system goes in, the sooner the wall panels for the next level can be set, and interior trades can start sooner on the floors already in place. The dry floor with C-joists (DF-J) builds easily into floor cassettes, and the gypsum-topped floor with C-joists (GT-J) prefabricates well as floor cassettes.
Why do the C-joist systems, DF-J and GT-J, lean on speed?
Because those two systems build easily, or prefabricate well, as floor cassettes. Wall-tech can shop-build the floors as prefabricated CFS floor panels and set them by crane in fast pick-and-set cycles. Floors and walls go up together, there is less on-site labor and less weather exposure for the framing, and interior trades can start sooner. GT-J still has a gypsum topping to pour and cure, which is a real trade-off, but the framing itself can still be prefabricated as cassettes. If the building needs longer spans or more room for MEP, a truss system may be the better fit, even if the cassette speed is the reason you looked at C-joists first.
What if my drawings already list a UL design?
A UL design number on the drawings is usually one way to meet the required fire-resistance rating; other listed assemblies may meet the same rating. The UL designs named in this post are a shortcut to common systems. They are common examples, not a complete list, and other UL-listed designs are available. Most UL designs aren't tied to one supplier, so the GC has choices. Ask your engineer of record whether an alternate listed assembly is acceptable for your project. Wall-tech is happy to share the assemblies we work with. Confirm the current listing, the project drawings and the authority having jurisdiction, and talk with the Wall-tech team before anyone freezes a design from a blog post.
What is a typical sound rating for these floors?
There is no single typical rating. For dwelling units and sleeping units, the International Building Code requires a minimum of STC 50 and IIC 50 when the floor-ceiling assembly is tested in the laboratory, or 45 when it is field-tested in the finished building. STC is the airborne rating (voices, television); IIC is the impact rating (footsteps, dropped objects). A higher number is better, and a floor can meet one and miss the other, especially IIC on a hard finish floor. For the dry floors (DF-J and DF-T), published manufacturer tests on H505-type assemblies measured STC 54 and IIC 27 with a bare floor, about STC 56 to 61 and IIC 51 to 57 with a hard surface finish over a sound mat underlayment, and about STC 56 to 57 and IIC 65 to 72 with carpet and pad. A bare or hard dry floor needs a sound mat to reach the code minimum IIC 50. For gypsum-topped floors, published tests on similar or matching assemblies are about STC 59 to 62 and IIC 41 to 77, depending on the topping, sound mat and finish floor. For concrete-topped floors, published ranges in the 2017 industry guide and related tests are about STC 50 to 60 and IIC 25 to 68, or higher with carpet and pad. The rating applies to the tested assembly, including the topping, underlayment, ceiling and finish floor, not to a system name alone. Confirm the numbers with your design team and the acoustical test reports, and talk with Wall-tech if you want help matching a floor to a sound target. Let us know how we can help.
Can I use a concrete-topped floor with Wall-tech walls?
Yes. Two of the systems in this comparison are concrete-topped floors: a truss or joist floor (CT-T) for projects that want a concrete floor feel, durability or extra mass, and longer spans with lots of MEP, and a clear-span deck-and-concrete floor (CT-CS) often used for hotels with short, repetitive spans. Both are durable, high-mass options, with the usual trade-offs of weight, placement, cure time and, for the clear-span floor, spans limited by the deck. Wall-tech will help you design the walls and the floor together when that is the right floor for the building.
What should I send Wall-tech for a preliminary budget?
Tell us your span, fire rating, sound targets and schedule, and send what plans you have. The Contact Us form does not require drawings up front; once we review your request, we will email you where to send them. You can also call 608-257-1595. We will help you weigh the floor and wall options and offer a cost-efficient framing solution and a preliminary budget. Let us know how we can help.